Newark, NJ · Building since 2013 General contractor · Construction manager · Design-builder CareersMediaPrequalifyProject map
Energy Infrastructure · 2023

Combined-Cycle Plant Upgrade

Turbine, piping and controls upgrades on a 620 MW plant, finished inside one planned outage with the unit back online early.

Owner
Confidential
Location
U.S.
Market
Energy Infrastructure
Delivery
EPC
Scale
620 MW
Completed
2023
The brief

Turbine, piping and controls upgrades delivered inside one planned outage window, with the unit back online early.

Every day offline cost the plant generating revenue, and the outage window was fixed long before engineering was done. Turbine work, piping replacement and a controls migration all competed for the same space, cranes and crews. Hidden conditions inside equipment could not be seen until the unit was opened.

How we built it

The approach.

  1. 01

    Outage schedule by the hour

    Thousands of outage activities were planned at hourly detail, with shift-by-shift updates to the critical path.

  2. 02

    Pre-outage work done early

    Piping spools, supports and control cabinets were fabricated and staged before shutdown, shrinking work inside the window.

  3. 03

    Contingencies priced ahead

    Likely findings inside the turbine were planned with parts and crews on standby, so discovery did not become delay.

  4. 04

    Controls proven on a simulator

    The new control logic was tested against a plant simulator before startup, cutting time spent tuning live equipment.

The outcome.

620 MWPlant capacity
1Planned outage window
0Days added to the outage
2023Unit back online early

“In an outage, the schedule is the product. Every hour we gave back was power the plant could sell.”

Outage manager, GilbertLanham
Energy Infrastructure

Planning something like this?

Share the project, the site and the date that matters. A senior builder will come back to you within one business day.