Airports · 2025

Airfield Apron & Terminal Modernization

A rebuilt apron, a new baggage hall and upgraded gates, phased so no airline lost a single departure slot.

Owner
Confidential
Location
U.S.
Market
Airports
Delivery
CM at-risk
Scale
22 acres
Completed
2025
The brief

A rebuilt apron, a new baggage hall and upgraded gates, phased so no airline lost a single departure slot.

Twenty-two acres of apron had to be replaced while aircraft parked, fueled and pushed back next to the work. Inside, the baggage hall was rebuilt under a terminal processing passengers every day. Each airline had its own slot schedule, and the airport needed a phasing plan that protected every one of them.

How we built it

The approach.

  1. 01

    Phasing built from slot schedules

    Airline departure data was mapped against apron phases, so each closure took gates out of service only when they were not needed.

  2. 02

    Concrete paving at night

    Apron panels were placed in overnight shifts with high-early-strength mixes, ready for aircraft within the agreed window.

  3. 03

    Airfield safety every shift

    Escorted vehicles, foreign object sweeps and daily coordination with operations kept the work invisible to pilots.

  4. 04

    Baggage system run before cutover

    The new carousels and conveyors ran thousands of test bags before the overnight switch from the old hall.

The outcome.

22Acres of apron rebuilt
0Departure slots lost
1New baggage claim hall
2025Final phase handed over

“The airline schedule was the real contract. We wrote our phasing plan in departure times.”

Project executive, GilbertLanham
Airports