Commercial · 2024

Corporate Headquarters Repositioning

An 18-floor office tower rebuilt into a modern headquarters while the tenant kept working above and below the construction.

Owner
Confidential
Location
U.S.
Market
Commercial
Delivery
General contracting
Scale
18 floors
Completed
2024
The brief

An occupied office tower rebuilt floor by floor into a modern headquarters, while the tenant kept working above and below.

The tenant never moved out. Floors were vacated in stacks, rebuilt and handed back while people worked one floor away. Demolition noise, riser shutdowns and elevator use all had to fit around a business that held meetings, hosted clients and ran on deadlines of its own.

How we built it

The approach.

  1. 01

    Stack plan as the master schedule

    Each floor had a vacate date, a rebuild duration and a move-back date, tracked in one schedule shared with the tenant’s move team.

  2. 02

    Noisy work after hours

    Core drilling, demolition and riser tie-ins ran on night shifts, with quiet work during the business day.

  3. 03

    One elevator, booked by the hour

    A dedicated service car moved debris and material on a published schedule, so tenant elevators stayed clean and on time.

  4. 04

    Floors returned complete

    Each floor was punched, cleaned and tested, including AV in every conference room, before employees moved back in.

The outcome.

18Floors rebuilt
0Days the tenant closed
1Shared stack-plan schedule
2024Final floor returned

“Our neighbors on this job were our client’s employees. Every night shift ended with a floor ready for their morning.”

Superintendent, GilbertLanham
Commercial